This is a Secret History Staff monograph by Gregory W. Pedlow and Donald E. Welzenbach of the Central Intelligence Agency, published in 1992. It gives a history of the CIA's manned overhead reconnaissance program from 1954 to 1974, covering the development and operation of the U-2 and the A-12 OXCART aircraft. It covers overflights of the Soviet Union, the 1960 downing of Francis Gary Powers, and later operations. One section is titled "U-2s, UFOs, and Operation BLUE BOOK."

From the source:Release of 2026-06-12 This CIA History Staff document chronicles the complete history of the U-2 and OXCART (A-12) high-altitude reconnaissance aircraft programs from 1954 to 1974, detailing their development, operations over the Soviet Union and other targets worldwide, the famous downing of Francis Gary Powers in 1960, organizational reforms following that incident, and the eventual transfer of operations from CIA to Air Force control. A more redacted version of this document has been available on CIA's public website.

  • p. 24 …April 1954. Lo.:khec:d Corporation. Advanced Devdopmcnt Projec:ts Divi~ion. Burbank. California. Sec,et
  • p. 58 …Pedlow, Burbank, California, 26 August 1988. 6eeret 11
  • p. 85 …how to transfer Lockheed employees from Burbank to Area 5 l without arousing a great deal…
  • p. 273 …SP-1362, "History of the OXCART Program," Lockheed Aircraft Corporation, Burbank, CA. I July 1968, p…
  • p. 287 …designed trailer truck that carried it from Burbank to Area 5 I. By 18 November 1959…
  • p. 296 …not test the OXCART aircraft at its Burbank facility, where the runway was too short and…
  • p. 297 …Construction began in September 1960; a C-47 shuttle s,ervice ferried work crews from Burbank…
  • p. 299 …The plane left Burbank on 26 February 1962 and arrived at Area 51 two days later…
  • p. 304 …into the engine nacelles during assembly at Burbank were sucked into the power plant during initial…
  • p. 372 …293 BUORL 22 Burbank. California 45 &eeret NOFe"N Index Burke. William 168 120 114 Byeloruss1a…
44
Sasret NOFORN
Chapter 2
use. Public Law 110, approved by the 81st Congress on 20 June 1949,
designates the Director of Central Intelligence as the only government
employee who can obligate Federal money without the use of vouch
ers. By using unvouchered funds, it is possible to eliminate competi
tive bidding and thereby limit the number of parties who know about
a given project. The use of unvouchered funds also speeds up the
Federal procurement cycle. A general contractor such as Lockheed
can purchase much, if not all, of the supplies needed for a project
without resorting at each step to the mandated procurement proce
dures involving public, competitive bidding. Covert contracting also
permits the use of second and third parties, many of them dummy
corporations or unwitting suppliers, thus hiding the intended destina
tion or use of the various purchases.
In mid-December 1954, President Eisenhower authorized DCI
Dulles to use $35 million from the Agency's Contingency Reserve Fund
to finance the U-2 project. Then on 22 December 1954, the Agency
signed a letter contract with Lockheed, using the codename Project
OARFISH. The Agency had proposed to give Lockheed "performance
specifications., rather than the standard Air Force "technical specifica
tions," which were more rigid and demanding, and Kelly Johnson agreed
that such a move would save a lot of money. Lockheed's original pro
posal to the Air Force in May l 954 had been $28 million for 20 U-2s
equipped with GE 173 engines. During negotiations with CIA General
Counsel Lawrence R. Houston, Lockheed changed its proposal to $26
million for 20 airframes plus a two-seat trainer model and spares; the Air
Force was to furnish the engines. Houston insisted that the Agency could
only budget $22.5 million for the airframes because it needed the balance
of the available $35 million for cameras and life-support gear. The two
sides finally agreed on a fixed-price contract with a provision for a re
view three-fourths of the way through to determine if the costs were
going to exceed the $22.5 million figure. The formal contract, No.
SP-1913, was signed on 2 March 1955 and called for the delivery of the
first U-2 in July 1955 and the last in November 1956. Meanwhile, to
keep work moving at Lockheed, Richard Bissell wrote a check for
$1,256,000 I ~nd mailed it to Kelly Johnson's
home on 21 February 1955.9
• John S. Warner. Oftice of the General Counsel, interview by Donald E. Welzenbach,
Washington, DC, tape recording, 5 Aug 1983 (S): OSA History, chap. 5, pp. 1-2 and annex
42 (TS Codeword): Johnson, "Log for Project X," 21 February 1955 .