This Black Vault release contains the Air Force's 2001 response from the 341st Space Wing FOIA office at Malmstrom AFB, Montana, to a request about the 16 March 1967 Echo Flight missile shutdown, with excerpts from 341st Strategic Missile Wing histories covering 1967 to early 1968. The histories say all ten Echo Flight launch facilities lost strategic alert almost simultaneously. Investigators could not find a logical cause and found rumors of UFOs near Echo Flight to be unfounded.

  • p. 39 …of Movement Security Alarm System on the Kings' re-entry vehicles G&C Vans was described…
  • p. 61 …Figure A 1377M (Kings I, II, IV, VAFB, STP III, KPA and EDL) for SCN/SIN…
  • p. 62 …Kit validation for the King I version and the Kings II through V modernized version to…

Read from the scan by GLM-OCR; expect the odd misread word.

FIRM NAME AND ADDRESS
THE BOEING COMPANY
P.O. BOX 1955 SEATTLE, WASH. 9824
(BOE 720)	ENGINEERING CHANGE PROPOSAL
FACILITY	DATE
27 December 1966
1	MCL NO. ATTACHMENT A1
2827	MFG CODE	SYSTEM DESIGNATION
WS133A	IECP NO. 528	TYPE I	REV.	COMPETITION
2	CONTRACTOR'S RECOMMENDED PRIORITY [ ] EMERGENCY [ ] URGENT [ X ] ROUTINE [ ] CONSTITUENTITY
3	CONTRACT END ITEM NOMINATION
Launch Facility
4	NAME OF PART OR LOWEST ASSEMBLY AFFECTED
Launch Facility Support Building
5	TITLE OF CHANGE
DC Supply for Isolation Relays - VRSA Channels 26 and 27 (LF)
6	DESCRIPTION OF CHANGE
Provide DC supply for the isolation relays being installed in VRSA channels 26 and 27 per ECP 1141. A typical DC supply circuit for these relays is shown on Attachment A Sketch 1.
ADDITIONAL DESCRIPTION:
Instructions for retest of VRSA Channels 26 and 27 and for personnel and weapon system safety will be required.
7	JUSTIFICATION FOR CHANGE
The isolation relays are being installed in VRSA channels 26 and 27 per ECP 1141. The DC power required for these relays is to be supplied from the RPIE power System. This FCIR initiates the required RPIE change.	REQUESTED BY PROCURING ACTIVITY PER REF:
FWG Meeting 90
DATE: 29 November 66
ATTACHMENT 0
PAGE 6
8	DEVELOPMENTAL REQUIREMENTS
N/A	ARE DESIGN REQ'D Yes DATE TBD
9	ALTERNATIVE SOLUTIONS
No alternate solutions are considered feasible
10	RECOMMENDED PRODUCTION EFFECTIVITY
N/A
11	ESTIMATED COST FOR CHANGE IN PRODUCTION
N/A
12	RECOMMENDED FOR RETROfit
Retrofit required to provide wiring changes for isolation relays to be installed by ECP 1141
13	RECOMMENDED RECOMMENDED EFFECTIVITY
VAFB, LF's 02 - 09; VAFB, EAFB, MTAFB, WAFB, FEWAFB - All Flights
HETF, LFSB	MOCKUP AFFECTED
YES X NO

About this file

Document, cited by the archive. The PDF is mirrored here; the original link is above. The text was read from the page images by GLM-OCR; expect the odd misread word. 88 pages are in the text index: search them above, or from the library's search.